Subscribe to our weekly newsletters
Subscribe to newsletter

 

Editor's Note:  Bachy Soletanche provide:-

Geotechnical SpecialistsGeotechnical Specialists
PilingPiling
Structural Retaining WallsStructural Retaining Walls
Ground Anchors Soil NailersGround Anchors Soil Nailers
Jet Grouting InjectionJet Grouting Injection GroutingGrouting
Environmental EngineeringEnvironmental Engineering
Building Design EngineersBuilding Design Engineers
Civil Engineering ProjectsCivil Engineering Projects

Request Information

Home
Include Article
Advertise
 

Links
Request Information
Terms of use
Contact

 

Request Facilities / Interiors product information

Request Architectural product information external

Request Architectural product information internal

Request Mechanical HVAC product information

Request Electrical product information

 

   

Bachy Soletanche goes piling by the dock at London’s Crossharbour site

Leading geotechnical specialist, Bachy Soletanche Limited has recently completed its first stage of piling works at Crossharbour, the high-profile development based in London City centre – constructing a secant wall around the perimeter of the site. The former London arena site is based in the heart of the Canary Wharf and Docklands business district and is one of the largest ongoing construction sites in London City centre.
The prestigious waterfront location is planned to provide a myriad of facilities comprising 1047 residential apartments, 285,846 sq ft of offices, a four star hotel and a combined 40,846 sq ft of retail, restaurants and leisure facilities.
Barry Osborn, contracts manager at Bachy Soletanche Limited, commented:
“Currently the site leaves a redundant space on the Millwall Inside Dock, however construction works are well underway as Bachy Soletanche has recently completed the secant wall piling works.”
“We were awarded the initial piling work for the secant wall in October last year and within four months the approximately 577lm long wall is now complete and ready for excavation” He added.
The initial secant wall contract comprises of approximately 970 secant piles, and due to the ground profile and the client requirement of a strict 1:200 tolerance two processes are being utilised to construct the wall.
Barry Osborn explains:
“The use of two different processes is required for the construction of the female and male piles
as the design requires complete accuracy. This is mainly due to the waterfront location of the site ensuring that the wall is completely watertight before excavation.”

The female piles were drilled to a depth of 14metres and constructed prior to the male piles using a bespoke piling method designed by Bachy Soletanche.
Barry Osborn commented:
“Once the female piles were installed the 485 male piles were ready to construct. These used a longer length casing at 17metres, had a stronger concrete mix and a different installation method to the female piles.”
The 750mm diameter male piles, with a 14metre depth were drilled using 17metre casings with the same length auger string. These piles were drilled utilising a cased continuous flight auger method (CSP), which was the preferred method due to the structure of the ground which at 14metres had a clay layer - forming a natural seal for the toe of the wall.
With the secant walls complete, Bachy Soletanche will remain on site as the geotechnical firm was awarded the main works contract for the bearing piles and the capping of the secant wall.Barry Osborn concluded:
“The original on-site time scale at Crossharbour was four months but then we were awarded the main works contract, extending the programme by another two months.”
“This caused a cross over for both the secant wall contract and the bearing piles contract, which resulted in the need for careful co-ordination to ensure the project ran smoothly. However, now the secant wall is complete we can concentrate on the bearing piles which are due to be completed in April”
 

Email: alex@manifestcomms.co.uk


News Archives - by Weeks  
2007 (weeks)  
1-2
3-4
5-6
7-8
9-10
11-12
13-14
15-16
17-18
19-20
21-22
23-24
25-26
27-28
29-30
31-32
33-34
35-36
37-38
39-40
41-42
43-44
45-46
47-48
49-50
51-52
 

Arundel Jones Associates Ltd
Hill Farm, Linton Hill, Maidstone, Kent ME17 4AL
Tel : 01622 745333
news@buildingdesign.co.uk

Registered in England and Wales No. 07334149
 

News Categories : Geotechnical Specialists
Piling
Structural Retaining Walls
Ground Anchors Soil Nailers
Jet Groating Injection Grouting
Environmental Engineering
Building Design Engineers
Civil Engineering Projects