Subscribe to our weekly newsletters
Subscribe to newsletter

 

Editor's Note:  iLevel™ Trus Joist® provide:-

Engineered floor systemsEngineered floor systems
Timber frame constructionTimber frame construction

Request Information

Home
Include Article
Advertise
 

Links
Request Information
Terms of use
Contact

 

Request Facilities / Interiors product information

Request Architectural product information external

Request Architectural product information internal

Request Mechanical HVAC product information

Request Electrical product information

 

   

iLevel™ Trus Joist® and Frame Wise face high-rise challenge

A new seven-storey timber frame residential development in the heart of Swindon town centre is nearing completion despite four developers deciding the site was not feasible for development using traditional brick and block.
The development, which utilises iLevel™ Trus Joist® engineered floors, is surrounded by existing high-rise buildings. The acute lack of site access, especially to the south elevation meant no scaffolding could be erected. This led to timber frame contractors, Frame Wise Ltd, based on the Welsh borders in Presteigne, constructing fully finished panels, including render, brickwork and windows, two metres inside the building line of each floor, before lifting them into position.
To overcome the problem of storage space on the former petrol station site, Frame Wise operated a ‘just in time’ construction schedule, making up to five deliveries a week to site, with each one craned immediately into position.
Nearly, 6,700 linear metres of TJI® joists in varying sizes were used for the project, supplied to Frame Wise by the Gloucester branch of iLevel™ Service Partner, Howarth Timber Engineering.
To meet the disproportionate collapse requirements of the current Building Regulations, over 80m3 of Parallam® PSL was installed around the perimeter of each floor to support its load should a wall panel be removed.
Commenting on the use of timber frame Richard James, contracts director for Frame Wise said: “With limited site access and storage, the project has been challenging. Nevertheless, timber frame offered the only real solution for the developer. Traditional alternatives would have required the space for access to be increased, which in turn would have reduced the overall size of the building, making the project less economically viable.”
The development by Contract House Builders Ltd comprises 61 one-bedroom apartments, close to the town’s railway station. It has been built on a 350mm thick concrete podium slab, under which there are 30 car parking spaces.
Each floor took approximately two weeks to construct. “By using timber frame we were able to work through the worst of this winter’s weather including snow that would have brought a normal concrete build to a standstill,” said Paul Philips, site manager for Contract House Builders. “What has been a 14 week structural build would have turned into more like 28 weeks.”
Besides reducing construction time compared to brick and block building methods, timber frame construction virtually eliminates snagging and maintenance costs due to ‘dry’ building methods. In addition, this approach increases thermal efficiency and sound installation as well as lowering dead loads and subsequently foundation costs.

Email: jeff@edsonevers.com
 


News Archives - by Weeks  
2007 (weeks)  
1-2
3-4
5-6
7-8
9-10
11-12
13-14
15-16
17-18
19-20
21-22
23-24
25-26
27-28
29-30
31-32
33-34
35-36
37-38
39-40
41-42
43-44
45-46
47-48
49-50
51-52
 

Arundel Jones Associates Ltd
Hill Farm, Linton Hill, Maidstone, Kent ME17 4AL
Tel : 01622 745333
news@buildingdesign.co.uk

Registered in England and Wales No. 07334149
 

News Categories : Engineered floor systems
Timber frame construction